Port of Mackay pulls ahead with new tug facility

24 Aug 2022

The Port of Mackay now boasts a new multi-million dollar purpose-built tug berth facility.

Transport and Main Roads Minister Mark Bailey said the $8.5 million investment had supported 60 good jobs in regional Queensland.

“The Port of Mackay has smashed out a record year of trade, proving just how strong Queensland’s export market is,” Mr Bailey said.

“Having the new tug berth facilities on site will position the Port to be able to take advantage of the new and diversified trade opportunities in the region, including rail and renewables.

“Construction also utilised local and regional contractors to ensure the economic dividends of this multi-million-dollar project are returned to regional communities.

“Thanks to the Palaszczuk Labor Government keeping Queensland Ports in public hands, it’s the people of Queensland who reap the benefits of this investment.”

North Queensland Bulk Ports (NQBP) Chief Executive Offficer Nicolas Fertin said North Queensland-based Pacific Marine Group Pty Ltd (PMG) had recently completed the new facility, supporting local jobs along the way.

“The use of regional and local contractors throughout the construction of the new facility was a focus,” Mr Fertin said.

“In total, around 60 regional jobs were supported during the project, almost triple the amount originally estimated,” he said.

The dedicated tug berth facility is located inside the secure port area and will cater for the existing tug fleet and provides flexibility for future growth.

The facility includes a floating pontoon and gangway which can berth up to two tugs. The berths can also accommodate bigger and more powerful tugs. Two pilot boat berths have also been included.

It is the largest in a series of recent, significant investments totalling $17 million aimed at boosting the port for current and future trade.

PMG Operations Manager Christo Wessels said the team was proud of the successful delivery of the project.

“Our team did a brilliant job considering there were a number of challenges along the way including a period of COVID shut downs which placed a strain on material supply chains and availability of qualified tradespeople,” Mr Wessels said.

Works also continue to progress on the Port’s $4 million Wharf 5 upgrades.

Queensland-based contractor V2R Projects are replacing the western access deck after 35 years of service.

Local jobs is also a strong feature of this project with Mackay, Rockhampon and Townsville-based companies being involved in the project through delivery of steel fabrication, scaffolding, craneage and concrete pre-casting.

Tug berth facility facts

  • $8.5 milllion investment
  • ~ 60 regional jobs
  • 35 metre floating pontoon
  • Pile length 38 metres
  • 42 metre gangway
  • ~ 260 tonnes steel used
  • ~ 4 km cable installed