North Queensland Bulk Ports Corporation (NQBP) has successfully completed maintenance dredging at the Port of Weipa for 2023.

Dredge vessel TSHD Brisbane and its supporting vessels have left the Port of Weipa after completing a 45-day program.

NQBP would like to commend all staff and contractors for their work in completing the dredging program in Weipa.

Around 780,000m3 of natural sediment was removed from the Port of Weipa and placed at the approved Dredge Material Placement Area (DMPA), in Albatross Bay.

NQBP would also like to thank the Weipa community for their patience and understanding during the project.

The TSHD Brisbane undertook over 400 trips to and from the DMPA without incident.

This is a testament to all involved including the local Weipa fishing and boating community.

Throughout the dredging, NQBP engaged with key stakeholders including the Weipa Technical Advisory and Consultative Committee (TACC). Members of the TACC include conservation groups, Traditional Owners, scientists, community, port users, and Commonwealth and State Governments.

The maintenance dredging was conducted in line with all approvals and permits, including a range of strict environmental conditions.

Environmental monitoring and management measures were implemented throughout the campaign to minimise the risk of any potential impacts on the marine environment.

NQBP has managed the annual maintenance dredging program at the Port of Weipa for more than 30 years.

Dredging was also completed at Amrun on behalf of Rio Tinto.

Image for download

Dredge vessel TSHD Brisbane underwent 400 trips without incident during the 45-day program.

North Queensland Bulk Ports Corporation contact:

Emilie Power | Community and Stakeholder Advisor